Expenses at each stage of the working

From projecting to finishing, see how much you will spend at each stage of the construction.

Maximum
Minimum

Projects and approvals
5%
12%
Preliminary Services
2%
4%
Foundations
3%
7%
Structure
14%
22%
Masonry
2%
5%
Finishing
4%
8%
Hydraulic Installation
7%
11%
Electric Installation
5%
7%
Waterproofing/Insulation/ Thermal Insulation
2%
4%
Window/door frames
4%
10%
Revetting/Finishing
15%
32%
Glasses
1%
2,5%
Painting
4%
6%
Complementary Services
0,5%
1%